Start with the permit, because it sets the roster
In Davidson County, a rooftop solar system goes through Metro Codes as an Electrical Photovoltaic permit. Metro says the applicant must be a contractor licensed and bonded with the Tennessee Department of Commerce and Insurance and registered with Codes, and that a licensed, experienced electrical installer has to do the work. A plans examiner checks that the roof can carry the extra load. Flat-roof and commercial projects need plans approved by a licensed architect or engineer before you submit. Nashville Electric Service approves the connection separately.
That one page tells you most of what you need to know. Solar on a roof in Nashville is electrical work with roofing attached. You can’t staff it with roofers alone, and you can’t hand the roof to an electrician and walk away.
Solar PV installer
What they do. Lay out the array, set attachments and racking, mount modules, and manage the wiring on the roof. A good one asks where the rafters are before drilling and works with your crew on flashing each attachment.
What they earn. BLS puts the national median for solar photovoltaic installers at $25.55 an hour, with an annual mean of $57,900 (BLS, May 2025). The wage data used here has no Tennessee row for this job, so treat that as a national figure.
Where to find them. Former solar company crews, roofers who have already worked on arrays, and electrical helpers who want roof work. Screen for fall protection habits and for how they handle a penetration, not just module count. The hire solar installers guide has a fuller list of what to ask.
Licensed electrician
What they do. Run the DC wiring from the array, set the inverter or microinverter gear, make the connection at the panel, and stand behind the work at inspection.
What Nashville requires. Metro Nashville requires a Metro license or registration for all electrical work. A journeyman passes the Metro journeyman exam and works under a licensed master. Licenses renew every year by April 1. If you hire someone licensed in another state, Metro can issue a temporary 6-month master or journeyman license.
What they earn. In the Nashville metro area, electricians earn a median of $30.45 an hour, with an annual mean of $66,710 (BLS, May 2025).
Where to find them. Look for electricians with service and panel work behind them. The tie-in at an older panel is often the hardest part of a residential solar job.
Master electrician or electrical contractor of record
What they do. Hold the license the permit runs under. This is the decision that shapes everything else. You either subcontract the electrical scope to a licensed electrical contractor or bring one onto your payroll.
What Tennessee requires. The state licenses electrical contractors for projects of $25,000 or more, through the Board for Licensing Contractors. A Nashville master electrician needs 6 years of electrical installation work, or an electrical engineering degree plus 2 years, and then the Metro exam. The Tennessee electrician license requirements page breaks down the state and Nashville rules side by side.
What to check. Look up any contractor license on TDCI Verify before you sign a subcontract. For a Nashville master or journeyman, ask for the Metro license number and confirm it with Metro Codes.
Apprentices and helpers
What they do. Carry material, pull wire, set racking and learn the work under supervision.
What Nashville requires. Apprentices must be enrolled in a USDOL-registered or nationally accredited program of at least 8,000 work hours and 600 hours of instruction. A master or journeyman has to be on the same jobsite. Nashville allows no more than 5 beginning electricians and apprentices per master or journeyman on a site. A beginning electrician must enroll in an apprenticeship after one year.
What they earn. Electrician helpers in the Nashville metro area earn a median of $22.23 an hour, with an annual mean of $43,620 (BLS, May 2025).
Where to find them. The Nashville Electrical JATC, sponsored by IBEW Local 429 and NECA, trains union apprentices. ABC Greater Tennessee runs a Construction Trades Academy in Nashville for merit shops. Both are worth a call if you want apprentices who are already enrolled, which keeps you inside Metro’s apprenticeship rule.
The roofing lead who owns the penetrations
What they do. Own every attachment that goes through the roof, the flashing detail used at each one, and the roof warranty conversation with the manufacturer.
This is usually someone already on your payroll. Name them on every solar job. The solar crew and the electrician both need one person to ask before they drill, and the homeowner needs one person to call if a leak shows up near the array a year later.
How the roles fit on a typical job
A residential array on a sloped roof often looks like this:
- One roofing lead from your crew for attachments and flashing.
- Two solar installers for layout, racking and modules.
- One licensed electrician for the wiring and tie-in, with a helper or apprentice.
- A master electrician or electrical contractor whose license the permit runs under.
A commercial flat roof adds an engineer or architect on the plans and usually more of everyone. Size the crew to the job. Don’t assume one person can cover two of these roles unless they hold the license for both.
Where to post and who to call
Indeed and Nashville trade Facebook groups bring volume, but you will sort through a lot of people who have never set foot on a roof or held a Metro license. Union shops can call the IBEW Local 429 hall. Staffing agencies can fill helper spots, though you still have to check licenses yourself.
The most direct route is a board where only electrical people look. Best Electrician Jobs is a job board just for electrical and low voltage work, solar techs included. You post the job yourself and applications come straight to you. If you’d rather not run the search, use Nashville electrical staffing: you describe the roles, site, start date and pay, and the person who runs the board calls candidates to check license, experience and travel before you interview them. Sending a request costs nothing, and you make every hiring decision.
Before the first panel goes up
- Decide who holds the electrical license on the permit.
- Confirm every electrician’s Metro license and every contractor’s state license.
- Check your apprentice ratio against Metro’s limit of 5 per master or journeyman.
- Name the roofing lead who signs off on each attachment.
- Put the NES approval and the Metro inspection on the schedule before you order modules.
Get those five right and the rest of the job is ordinary roofing and ordinary wiring, done by the right people in the right order.